Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-256-08-56 11-2358U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 81% 11-SD-5-35.7/38.5 Federal Project: NONE Progress payment No. 12 Payment period ending: 08-20-08 COFFMAN SPECIALTIES INC 4375 JUTLAND DRIVE STE 260 SAN DIEGO CA 92117 Escrow No. 02332 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,064,642.84 0.00 2.a. Extra Work 490,711.98 -834.46 b. Adjustment Comp. 173,042.40 0.00 3. Materials on Hand 289,714.41 243,543.44 4. Earned Subject to Retention 25,018,111.63 242,708.98 5. Mobilization 3,225,000.00 0.00 6. Total Work Completed 27,953,397.22 7. Deductions -767,280.92 0.00 8. a.Contract Retentions -1,250,905.58 -12,135.45 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,224,925.13 230,573.53 10. Reduction Amt to Escrow 11. Payment to Escrow 1,250,900.00 12. Net Pymt. this Estimate 230,573.53