Dept. of Trans. PROGRESS Serial No. Contract No. 08-295-14-54 11-2358U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 96% 11-SD-5-35.7/38.5 Federal Project: NONE Progress payment No. 14 Payment period ending: 10-20-08 COFFMAN SPECIALTIES INC 4375 JUTLAND DRIVE STE 260 SAN DIEGO CA 92117 Escrow No. 02332 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,595,870.69 779,175.15 2.a. Extra Work 1,029,860.43 225,644.29 b. Adjustment Comp. 170,385.53 -2,656.87 3. Materials on Hand 42,519.61 -30,213.59 4. Earned Subject to Retention 26,838,636.26 971,948.98 5. Mobilization 3,225,000.00 0.00 6. Total Work Completed 30,021,116.65 7. Deductions -57,219.93 -10,000.00 8. a.Contract Retentions -1,341,931.81 -48,597.45 b. Unsatisfactory Prog. -48,597.45 -48,597.45 c. Reduction after 95% Comp. 9. Total pay to Contractor 28,615,887.07 864,754.08 10. Reduction Amt to Escrow 11. Payment to Escrow 1,341,930.00 12. Net Pymt. this Estimate 864,754.08