Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-033-06-47 11-2358U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 11-SD-5-35.7/38.5 Federal Project: NONE Progress payment No. 18 Payment period ending: 01-20-09 COFFMAN SPECIALTIES INC 4375 JUTLAND DRIVE STE 260 SAN DIEGO CA 92117 Escrow No. 02332 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,733,128.73 0.00 2.a. Extra Work 1,282,541.66 0.00 b. Adjustment Comp. 168,613.23 0.00 3. Materials on Hand 764.79 0.00 4. Earned Subject to Retention 29,185,048.41 0.00 5. Mobilization 3,225,000.00 0.00 6. Total Work Completed 32,409,283.62 7. Deductions -129,629.93 155,006.04 8. a.Contract Retentions -1,459,252.42 0.00 b. Unsatisfactory Prog. 0.00 165,918.06 c. Reduction after 95% Comp. 9. Total pay to Contractor 30,821,166.06 320,924.10 10. Reduction Amt to Escrow 11. Payment to Escrow 1,459,250.00 12. Net Pymt. this Estimate 320,924.10