Dept. of Trans. PROGRESS Serial No. Contract No. 04-170-13-36 11-236204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 78% 11-IMP-111-8.8/12.6 Federal Project: ACNH-P111(7) Progress payment No. 04 Payment period ending: 06-20-04 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 426,235.42 309,911.58 2.a. Extra Work 5,327.32 0.00 b. Adjustment Comp. 108.84 0.00 3. Materials on Hand 4. Earned Subject to Retention 431,671.58 309,911.58 5. Mobilization 11,190.00 2,797.50 6. Total Work Completed 442,861.58 7. Deductions 8. a.Contract Retentions -21,583.58 -9,407.58 b. Unsatisfactory Prog. -15,495.58 -15,495.58 c. Reduction after 95% Comp. 9. Total pay to Contractor 405,782.42 287,805.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 287,805.92