Dept. of Trans. FINAL Serial No. Contract No. 06-052-15-38 11-237074 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-8-R48.4/R49.3 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-11-05 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 815,125.63 0.00 2.a. Extra Work 2,141.54 0.00 b. Adjustment Comp. -3,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 814,267.17 0.00 5. Mobilization 6. Total Work Completed 814,267.17 7. Deductions -574.67 10,000.00 8. a.Contract Retentions -40,304.22 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 40,304.22 0.00 9. Total pay to Contractor 813,692.50 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00