Dept. of Trans. PROGRESS Serial No. Contract No. 17-265-15-20 11-237964 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 69% Location: Federal Project: 11-SD-8-5.4/10.6 NHPI-008-1(321) Progress payment No. 009 Payment period ending: 09-20-17 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY PLACE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,455,579.50 171,500.50 2. a. Extra Work 26,297.60 7,096.47 b. Adustment Comp. 13,082.00 1,626.14 3. Materials on Hand 321.85 -27,528.09 4. Earned Subject to Retention 2,495,280.95 152,695.02 5. Mobilization 475,000.00 0.00 6. Total Work Completed 2,969,959.10 7. Deductions -10,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,960,280.95 147,695.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,695.02