Dept. of Trans. PROGRESS Serial No. Contract No. 18-053-07-27 11-237964 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 100% Location: Federal Project: 11-SD-8-5.4/10.6 NHPI-008-1(321) Progress payment No. 014 Payment period ending: 02-20-18 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,664,049.54 48,814.00 2. a. Extra Work 68,623.19 11,919.21 b. Adustment Comp. 29,233.35 16,151.35 3. Materials on Hand 4. Earned Subject to Retention 3,761,906.08 76,884.56 5. Mobilization 500,000.00 0.00 6. Total Work Completed 4,261,906.08 7. Deductions -5,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -52,183.07 -7,688.46 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,204,723.01 67,196.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,196.10