Dept. of Trans. 95% REDUCTION Serial No. Contract No. 07-080-14-28 11-238504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-805-10.8/11.8 Federal Project: NONE Progress payment No. 12 Payment period ending: 03-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,533,200.90 8,292.88 2.a. Extra Work 113,314.54 0.00 b. Adjustment Comp. 11,740.83 -44.74 3. Materials on Hand 4. Earned Subject to Retention 1,658,256.27 8,248.14 5. Mobilization 160,000.00 0.00 6. Total Work Completed 1,818,256.27 7. Deductions 8. a.Contract Retentions -82,912.81 -412.40 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 35,585.95 1,021.48 9. Total pay to Contractor 1,770,929.41 8,857.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,857.22