Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-121-13-35 11-238504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-805-10.8/11.8 Federal Project: NONE Progress payment No. 13 Payment period ending: 03-14-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,540,760.90 7,560.00 2.a. Extra Work 111,872.48 -1,442.06 b. Adjustment Comp. 6,902.14 -4,838.69 3. Materials on Hand 4. Earned Subject to Retention 1,659,535.52 1,279.25 5. Mobilization 160,000.00 0.00 6. Total Work Completed 1,819,535.52 7. Deductions 8. a.Contract Retentions -82,912.81 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 82,912.81 47,326.86 9. Total pay to Contractor 1,819,535.52 48,606.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,606.11