Dept. of Trans. PROGRESS Serial No. Contract No. 06-265-15-02 11-241504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 30% 11-SD-163-8.3/8.9 Federal Project: STPL-6211(46) Progress payment No. 05 Payment period ending: 09-20-06 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,609,682.30 778,249.13 2.a. Extra Work 68,807.53 18,088.54 b. Adjustment Comp. -2,228.00 -2,228.00 3. Materials on Hand 4. Earned Subject to Retention 2,676,261.83 794,109.67 5. Mobilization 422,750.00 89,000.00 6. Total Work Completed 3,099,011.83 7. Deductions -43,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,056,011.83 893,109.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 893,109.67