Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-14-27 11-241504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 37% 11-SD-163-8.3/8.9 Federal Project: STPL-6211(46) Progress payment No. 06 Payment period ending: 10-20-06 ERRECAS INC P O BOX 640 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,627,946.90 1,018,264.60 2.a. Extra Work 115,959.20 47,151.67 b. Adjustment Comp. -2,228.00 0.00 3. Materials on Hand 413,420.00 413,420.00 4. Earned Subject to Retention 4,155,098.10 1,478,836.27 5. Mobilization 422,750.00 0.00 6. Total Work Completed 4,164,428.10 7. Deductions -23,000.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,554,848.10 1,498,836.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,498,836.27