Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-07-34 11-241514 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 23% Location: Federal Project: 11-SD-163-8.4/9.4 NONE Progress payment No. 009 Payment period ending: 12-20-15 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DRIVE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,909,529.85 292,704.50 2. a. Extra Work 63,547.26 13,795.33 b. Adustment Comp. 3. Materials on Hand 203,559.12 0.00 4. Earned Subject to Retention 2,176,636.23 306,499.83 5. Mobilization 760,000.00 0.00 6. Total Work Completed 2,733,077.11 7. Deductions -6,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,930,636.23 306,499.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 306,499.83