Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-065-14-55 11-241904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-78-20.7/R21.3 Federal Project: ACST-P078(102) PH-P078(102) Progress payment No. 24 Payment period ending: 11-20-06 R J BULLARD CONSTRUCTION INC P O BOX 1577 BONSALL CA 920031577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,749,515.23 -4,137.15 2.a. Extra Work 372,625.33 -5,924.69 b. Adjustment Comp. 351,048.26 3,121.14 3. Materials on Hand 4. Earned Subject to Retention 2,473,188.82 -6,940.70 5. Mobilization 240,000.00 0.00 6. Total Work Completed 2,713,188.82 7. Deductions -569,536.35 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,143,652.47 3,059.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,059.30