Dept. of Trans. FINAL Serial No. Contract No. 09-251-12-34 11-241924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-78-20.9/R21.3 Federal Project: ACST-P078(104) PH-P078(104) Progress payment No. 10 Payment period ending: 06-29-07 WIER CONSTRUCTION CORPORATION 2255 BARHAM DRIVE ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 402,981.29 0.00 2.a. Extra Work 318,845.93 0.00 b. Adjustment Comp. 86,076.37 80,000.00 3. Materials on Hand 4. Earned Subject to Retention 807,903.59 80,000.00 5. Mobilization 92,170.00 0.00 6. Total Work Completed 900,073.59 7. Deductions -373.80 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 899,699.79 80,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 80,000.00