Dept. of Trans. PROGRESS Serial No. Contract No. 18-141-09-31 11-244004 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 58% Location: Federal Project: 11-SD-5-3.9/9.2 ACNH-OI00-5(634) Progress payment No. 015 Payment period ending: 05-20-18 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,649,245.27 40.00 2. a. Extra Work 1,286,355.36 75,662.36 b. Adustment Comp. -1,287,287.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,648,313.40 75,702.36 5. Mobilization 791,966.25 0.00 6. Total Work Completed 7,440,279.65 7. Deductions -74,449.66 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,365,829.99 75,702.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,702.36