Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-14-37 11-244004 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 63% Location: Federal Project: 11-SD-5-3.9/9.2 ACNH-OI00-5(634) Progress payment No. 016 Payment period ending: 06-20-18 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,660,942.27 11,697.00 2. a. Extra Work 1,332,938.71 46,583.35 b. Adustment Comp. -1,289,846.46 -2,559.23 3. Materials on Hand 4. Earned Subject to Retention 6,704,034.52 55,721.12 5. Mobilization 791,966.25 0.00 6. Total Work Completed 7,496,000.77 7. Deductions -74,449.66 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,421,551.11 55,721.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 55,721.12