Dept. of Trans. PROGRESS Serial No. Contract No. 18-354-15-19 11-244004 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 88% Location: Federal Project: 11-SD-5-3.9/9.2 ACNH-OI00-5(634) Progress payment No. 022 Payment period ending: 12-20-18 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA #200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,688,419.77 3,680.00 2. a. Extra Work 1,388,593.77 6,531.23 b. Adustment Comp. -1,289,793.38 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,787,220.16 10,211.23 5. Mobilization 791,966.25 0.00 6. Total Work Completed 7,579,186.41 7. Deductions -83,850.34 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,495,336.07 10,211.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,211.23