Dept. of Trans. FINAL Serial No. Contract No. 08-303-13-25 11-246514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-75-R20.5/R21.9 Federal Project: NONE Progress payment No. 22 Payment period ending: 04-14-08 WIER CONSTRUCTION CORPORATION 2255 BARHAM DRIVE ESCONDIDO CA 92029 Escrow No. 02292 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,227,032.00 0.00 2.a. Extra Work 164,401.50 82,603.55 b. Adjustment Comp. -467,418.22 243,807.90 3. Materials on Hand 4. Earned Subject to Retention 6,924,015.28 326,411.45 5. Mobilization 489,600.00 0.00 6. Total Work Completed 7,413,615.28 7. Deductions 8. a.Contract Retentions -296,668.12 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 296,668.12 0.00 9. Total pay to Contractor 7,413,615.28 326,411.45 10. Reduction Amt to Escrow -296,660.00 0.00 11. Payment to Escrow 296,660.00 12. Net Pymt. this Estimate 326,411.45