Dept. of Trans. FINAL Serial No. Contract No. 08-253-14-01 11-246544 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-75-R20.5/R21.8 Federal Project: NONE Progress payment No. 11 Payment period ending: 07-01-08 WIER CONSTRUCTION CORPORATION 2255 BARHAM DR ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 496,140.26 0.00 2.a. Extra Work 32,220.10 0.00 b. Adjustment Comp. 41.18 0.00 3. Materials on Hand 4. Earned Subject to Retention 528,401.54 0.00 5. Mobilization 151,718.75 0.00 6. Total Work Completed 680,120.29 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -23,579.02 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 23,579.02 0.00 9. Total pay to Contractor 680,120.29 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00