Dept. of Trans. PROGRESS Serial No. Contract No. 03-234-13-31 11-247704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 46% 11-SD-52-8.5/9.1 Federal Project: NONE Progress payment No. 19 Payment period ending: 08-20-03 BELAIRE WEST LANDSCAPE INC P O BOX 6270 BUENA PARK CA 90622 Escrow No. 01931 Total Estimate This Estimate 1. Contract Itms Without Mobil. 358,159.10 3,389.50 2.a. Extra Work 8,738.58 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 366,897.68 3,389.50 5. Mobilization 20,000.00 0.00 6. Total Work Completed 386,897.68 7. Deductions 0.00 5,000.00 8. a.Contract Retentions -18,344.88 -169.47 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 368,552.80 8,220.03 10. Reduction Amt to Escrow 11. Payment to Escrow 18,170.00 12. Net Pymt. this Estimate 8,220.03