Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 03-223-13-33 11-247904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 80% 11-SD-5-R0.2/1.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-03 QUALITY FENCE CO INC 14929 GARFIELD AVENUE PARAMOUNT CA 90723 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 173,755.00 42,362.00 2.a. Extra Work 17,696.60 11,787.50 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 191,451.60 54,149.50 5. Mobilization 6. Total Work Completed 191,451.60 7. Deductions 8. a.Contract Retentions -9,572.58 -2,635.28 b. Unsatisfactory Prog. 0.00 6,792.91 c. Reduction after 95% Comp. 9. Total pay to Contractor 181,879.02 58,307.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,307.13