Dept. of Trans. PROGRESS Serial No. Contract No. 04-145-13-47 11-253504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 34% 11-SD-125-11.5/12.2 Federal Project: ACNH-P125(16) Progress payment No. 05 Payment period ending: 05-20-04 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1702 KAISER AVENUE IRVINE CA 926145706 Escrow No. 02166 Total Estimate This Estimate 1. Contract Itms Without Mobil. 548,408.40 47,851.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 548,408.40 47,851.50 5. Mobilization 6. Total Work Completed 548,408.40 7. Deductions 0.00 3,553.35 8. a.Contract Retentions -51,495.41 -1,439.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 496,912.99 49,965.13 10. Reduction Amt to Escrow 11. Payment to Escrow 51,490.00 12. Net Pymt. this Estimate 49,965.13