Dept. of Trans. PROGRESS Serial No. Contract No. 06-171-14-07 11-253504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-11.5/12.2 Federal Project: ACNH-P125(16) Progress payment No. 29 Payment period ending: 06-20-06 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1702 KAISER AVENUE IRVINE CA 926145706 Escrow No. 02166 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,509,263.35 2,100.00 2.a. Extra Work 118,059.16 0.00 b. Adjustment Comp. 2,805.84 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,630,128.35 2,100.00 5. Mobilization 6. Total Work Completed 2,630,128.35 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions -131,506.42 -105.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,497,621.93 995.00 10. Reduction Amt to Escrow 11. Payment to Escrow 131,290.00 12. Net Pymt. this Estimate 995.00