Dept. of Trans. PROGRESS Serial No. Contract No. 06-355-15-09 11-254304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 78% 11-SD-8-2.2/2.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-20-06 3 D ENTERPRISES INCORPORATED 2180 GARNET AVE STE 2C SAN DIEGO CA 92109 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 612,441.84 156,743.36 2.a. Extra Work 8,734.81 1,994.99 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 621,176.65 158,738.35 5. Mobilization 40,737.00 0.00 6. Total Work Completed 661,913.65 7. Deductions 8. a.Contract Retentions -31,058.83 -7,936.91 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 630,854.82 150,801.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150,801.44