Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-14-24 11-256204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-IMP-111-11.4/22.2 Federal Project: NONE Progress payment No. 32 Payment period ending: 11-20-08 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY RD FLR 4 ORANGE CA 92868 Escrow No. 02224 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,237,130.29 1,961.94 2.a. Extra Work 23,096.81 0.00 b. Adjustment Comp. -8,686.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,251,541.10 1,961.94 5. Mobilization 61,000.00 0.00 6. Total Work Completed 1,312,541.10 7. Deductions 8. a.Contract Retentions -62,577.06 -98.10 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,249,964.04 1,863.84 10. Reduction Amt to Escrow 11. Payment to Escrow 62,470.00 12. Net Pymt. this Estimate 1,863.84