Dept. of Trans. PROGRESS Serial No. Contract No. 09-265-13-58 11-256204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-IMP-111-11.4/22.2 Federal Project: NONE Progress payment No. 42 Payment period ending: 09-20-09 P AND D LANDSCAPE MANAGEMENT SERVICES 999 TOWN AND COUNTRY RD FLR 4 ORANGE CA 92868 Escrow No. 02224 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,263,499.86 9,495.91 2.a. Extra Work 53,513.53 2,487.54 b. Adjustment Comp. -8,686.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,308,327.39 11,983.45 5. Mobilization 61,000.00 0.00 6. Total Work Completed 1,369,327.39 7. Deductions -1,000.00 0.00 8. a.Contract Retentions -65,416.37 -599.17 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,302,911.02 11,384.28 10. Reduction Amt to Escrow 11. Payment to Escrow 65,410.00 12. Net Pymt. this Estimate 11,384.28