Dept. of Trans. PROGRESS Serial No. Contract No. 05-298-13-15 11-257104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 99% 11-SD-76-11.8/12.1 Federal Project: HP21-6211(3) L-6211(3) Progress payment No. 09 Payment period ending: 10-20-05 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,548,118.78 340,580.98 2.a. Extra Work 20,640.23 8,350.83 b. Adjustment Comp. -4,359.24 -4,848.75 3. Materials on Hand 4. Earned Subject to Retention 1,564,399.77 344,083.06 5. Mobilization 172,000.00 0.00 6. Total Work Completed 1,736,399.77 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,716,399.77 334,083.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 334,083.06