Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-355-15-02 11-257104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-76-11.8/12.1 Federal Project: HP21-6211(3) L-6211(3) Progress payment No. 11 Payment period ending: 12-15-05 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,590,305.27 14,141.49 2.a. Extra Work 47,184.16 12,622.56 b. Adjustment Comp. -4,359.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,633,130.19 26,764.05 5. Mobilization 172,000.00 0.00 6. Total Work Completed 1,805,130.19 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,795,130.19 16,764.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,764.05