Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-15-10 11-257154 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 11% Location: Federal Project: 11-SD-76-12.1/R17.7 STPL-6211(114) TPF-2012(1) Progress payment No. 005 Payment period ending: 02-20-15 AMES CONSTRUCTION INC 2000 AMES DRIVE BURNSVILLE, MN 55306 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,987,428.13 1,648,181.60 2. a. Extra Work 124,748.93 86,375.25 b. Adustment Comp. 1,725.00 1,725.00 3. Materials on Hand 598,324.00 598,324.00 4. Earned Subject to Retention 5,712,226.06 2,334,605.85 5. Mobilization 3,730,000.00 0.00 6. Total Work Completed 8,843,902.06 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,437,226.06 2,334,605.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,334,605.85