Dept. of Trans. PROGRESS Serial No. Contract No. 04-356-13-48 11-258014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 69% 11-SD-163-1.2/2.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-04 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 02187 Total Estimate This Estimate 1. Contract Itms Without Mobil. 429,005.60 344,380.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 129,808.15 129,808.15 4. Earned Subject to Retention 558,813.75 474,189.05 5. Mobilization 40,000.00 20,000.00 6. Total Work Completed 469,005.60 7. Deductions 8. a.Contract Retentions -27,940.69 -19,478.22 b. Unsatisfactory Prog. -23,709.45 -23,709.45 c. Reduction after 95% Comp. 9. Total pay to Contractor 547,163.61 451,001.38 10. Reduction Amt to Escrow 11. Payment to Escrow 27,940.00 12. Net Pymt. this Estimate 451,001.38