Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-179-13-40 11-258014 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-163-1.2/2.4 Federal Project: NONE Progress payment No. 23 Payment period ending: 09-01-06 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 02187 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,013,415.92 0.00 2.a. Extra Work 140,359.06 0.00 b. Adjustment Comp. 31,907.81 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,185,682.79 0.00 5. Mobilization 40,000.00 0.00 6. Total Work Completed 1,225,682.79 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -56,268.59 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 56,268.59 0.00 9. Total pay to Contractor 1,225,682.79 10,000.00 10. Reduction Amt to Escrow -56,230.00 0.00 11. Payment to Escrow 56,230.00 12. Net Pymt. this Estimate 10,000.00