Dept. of Trans. PROGRESS Serial No. Contract No. 05-203-14-00 11-258024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 9% 11-SD-163-0.9/2.8 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-05 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02193 Total Estimate This Estimate 1. Contract Itms Without Mobil. 363,769.09 96,758.23 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 363,769.09 96,758.23 5. Mobilization 58,000.00 2,900.00 6. Total Work Completed 421,769.09 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -18,188.45 -4,837.91 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 403,580.64 104,820.32 10. Reduction Amt to Escrow 11. Payment to Escrow 18,180.00 12. Net Pymt. this Estimate 104,820.32