Dept. of Trans. PROGRESS Serial No. Contract No. 05-355-15-02 11-258024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 21% 11-SD-163-0.9/2.8 Federal Project: NONE Progress payment No. 10 Payment period ending: 12-20-05 DIVERSIFIED LANDSCAPE CO 33801 WASHINGTON STREET WINCHESTER CA 92596 Escrow No. 02193 Total Estimate This Estimate 1. Contract Itms Without Mobil. 405,957.78 3,661.65 2.a. Extra Work 3,762.82 774.99 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 409,720.60 4,436.64 5. Mobilization 58,000.00 0.00 6. Total Work Completed 467,720.60 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions -20,486.03 -221.83 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 446,234.57 3,214.81 10. Reduction Amt to Escrow 11. Payment to Escrow 20,260.00 12. Net Pymt. this Estimate 3,214.81