Dept. of Trans. PROGRESS Serial No. Contract No. 06-171-14-14 11-259204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 81% 11-SD-76-R0.1/R2.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,104,116.52 538,212.29 2.a. Extra Work 149,407.58 4,663.13 b. Adjustment Comp. -5,303.63 -5,303.63 3. Materials on Hand 4. Earned Subject to Retention 1,248,220.47 537,571.79 5. Mobilization 323,000.00 0.00 6. Total Work Completed 1,571,220.47 7. Deductions -1,200.00 8,800.00 8. a.Contract Retentions -65,198.60 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,504,821.87 546,371.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 546,371.79