Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-14-53 11-259204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 86% 11-SD-76-R0.1/R2.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 08-20-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,454,402.78 445,321.26 2.a. Extra Work 149,407.58 0.00 b. Adjustment Comp. -700.74 4,602.89 3. Materials on Hand 4. Earned Subject to Retention 2,603,109.62 449,924.15 5. Mobilization 340,000.00 0.00 6. Total Work Completed 2,943,109.62 7. Deductions -1,200.00 0.00 8. a.Contract Retentions -130,155.48 -22,496.21 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,811,754.14 427,427.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 427,427.94