Dept. of Trans. PROGRESS Serial No. Contract No. 06-265-15-09 11-259204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 97% 11-SD-76-R0.1/R2.2 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-20-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,999,556.64 545,153.86 2.a. Extra Work 152,289.36 2,881.78 b. Adjustment Comp. -700.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,151,145.26 548,035.64 5. Mobilization 340,000.00 0.00 6. Total Work Completed 3,491,145.26 7. Deductions -11,200.00 -10,000.00 8. a.Contract Retentions -157,557.26 -27,401.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,322,388.00 510,633.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 510,633.86