Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-333-10-45 11-259204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-76-R0.1/R2.2 Federal Project: NONE Progress payment No. 08 Payment period ending: 10-23-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,143,442.96 27,323.27 2.a. Extra Work 192,375.57 16,717.10 b. Adjustment Comp. -570.53 -195.53 3. Materials on Hand 4. Earned Subject to Retention 3,335,248.00 43,844.84 5. Mobilization 340,000.00 0.00 6. Total Work Completed 3,675,248.00 7. Deductions -14,809.82 -13,609.82 8. a.Contract Retentions -164,570.16 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 164,570.16 164,570.16 9. Total pay to Contractor 3,660,438.18 194,805.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 194,805.18