Dept. of Trans. FINAL Serial No. Contract No. 07-033-12-16 11-259204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-76-R0.1/R2.2 Federal Project: NONE Progress payment No. 09 Payment period ending: 10-23-06 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,143,442.96 0.00 2.a. Extra Work 207,034.41 14,658.84 b. Adjustment Comp. -12,570.53 -12,000.00 3. Materials on Hand 4. Earned Subject to Retention 3,337,906.84 2,658.84 5. Mobilization 340,000.00 0.00 6. Total Work Completed 3,677,906.84 7. Deductions -2,077.50 12,732.32 8. a.Contract Retentions -164,570.16 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 164,570.16 0.00 9. Total pay to Contractor 3,675,829.34 15,391.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,391.16