Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-12-53 11-259304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 59% 11-SD-5-R66.5/R68.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-08 G I M GENERAL ENGINEERING 916 MORNING SUN DRIVE ENCINITAS CA 92024 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 441,400.00 250,750.00 2.a. Extra Work 10,575.82 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 451,975.82 250,750.00 5. Mobilization 50,000.00 2,500.00 6. Total Work Completed 501,975.82 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -22,598.79 -11,334.79 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 469,377.03 231,915.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 231,915.21