Dept. of Trans. PROGRESS Serial No. Contract No. 12-171-14-04 11-259804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 19% 11-SD-78-15.3/15.7 Federal Project: 6211-107E Progress payment No. 04 Payment period ending: 06-20-12 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,445,352.73 1,056,888.22 2.a. Extra Work 15,193.67 6,057.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,460,546.40 1,062,946.15 5. Mobilization 817,000.00 172,000.00 6. Total Work Completed 3,277,546.40 7. Deductions -7,600.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,269,946.40 1,231,946.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,231,946.15