Dept. of Trans. PROGRESS Serial No. Contract No. 06-114-14-27 11-260104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 62% 11-IMP-86-20.0/20.3 Federal Project: ACST-P086(70) PHG-P086(70) Progress payment No. 02 Payment period ending: 04-20-06 H M S CONSTRUCTION INC 1225 LINDA VISTA DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 162,307.11 136,392.74 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 162,307.11 136,392.74 5. Mobilization 26,875.50 12,730.50 6. Total Work Completed 189,182.61 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 189,182.61 149,123.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,123.24