Dept. of Trans. FINAL Serial No. Contract No. 06-307-11-54 11-260104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-86-20.0/20.3 Federal Project: ACST-P086(70) PHG-P086(70) Progress payment No. 06 Payment period ending: 07-12-06 H M S CONSTRUCTION INC 1225 LINDA VISTA DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 396,668.16 0.00 2.a. Extra Work 8,686.83 1,545.89 b. Adjustment Comp. 6,609.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 411,964.05 1,545.89 5. Mobilization 28,290.00 0.00 6. Total Work Completed 440,254.05 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 440,254.05 11,545.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,545.89