Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-14-17 11-260714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 14% 11-SD-15-M18.8/M21.9 Federal Project: HPLU-6211(64) N-6211(64) Progress payment No. 07 Payment period ending: 02-20-09 SIERRA LANDSCAPE CO 73 771 DINAH SHORE DRIVE PALM DESERT CA 92211 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 504,469.64 80,915.44 2.a. Extra Work 4,643.00 4,643.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 509,112.64 85,558.44 5. Mobilization 114,000.00 24,000.00 6. Total Work Completed 623,112.64 7. Deductions -25,693.46 5,405.76 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 597,419.18 114,964.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,964.20