Dept. of Trans. PROGRESS Serial No. Contract No. 09-327-14-53 11-260724 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 64% 11-SD-15-M21.9/M23.9 Federal Project: HPLU-6211(80) Progress payment No. 08 Payment period ending: 11-20-09 EAST BAY CONSTRUCTION COMPANY INC 41120 ELM STREET STE G MURRIETA CA 92562 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 483,027.44 94,097.68 2.a. Extra Work 32,239.14 9,504.00 b. Adjustment Comp. 3. Materials on Hand 0.00 -41,404.45 4. Earned Subject to Retention 515,266.58 62,197.23 5. Mobilization 23,750.00 0.00 6. Total Work Completed 539,016.58 7. Deductions -1,927.48 3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 537,089.10 65,197.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,197.23