Dept. of Trans. PROGRESS Serial No. Contract No. 14-170-15-10 11-2607C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 47% 11-SD-15-23.8/26.2 Federal Project: NONE Progress payment No. 17 Payment period ending: 06-20-14 3D ENTERPRISES, INC. 7964 ARJONS DRIVE, SUITE I SAN DIEGO, CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 279,802.32 15,698.48 2.a. Extra Work 10,806.43 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 290,608.75 15,698.48 5. Mobilization 6. Total Work Completed 290,608.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 290,608.75 15,698.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,698.48