Dept. of Trans. PROGRESS Serial No. Contract No. 04-266-14-56 11-260804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 100% 11-SD-805-16.9/17.6 Federal Project: ACIM-805-1(591) Progress payment No. 06 Payment period ending: 09-20-04 ZONDIROS CORPORATION 1833 DIAMOND STREET STE 102 SAN DIEGO CA 92069 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 353,199.88 4,853.25 2.a. Extra Work 249,594.12 95,508.31 b. Adjustment Comp. 19,846.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 622,640.00 100,361.56 5. Mobilization 6. Total Work Completed 622,640.00 7. Deductions -2,000.00 -1,000.00 8. a.Contract Retentions -31,132.00 -5,018.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 589,508.00 94,343.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,343.48