Dept. of Trans. PROGRESS Serial No. Contract No. 10-026-07-24 11-261504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 35% 11-IMP-8-R31.3/ .0 Federal Project: ACHS-X025(28) STPG-X025(28) Progress payment No. 05 Payment period ending: 01-20-10 R S M 2 CONTRACTORS INC 8191 CENTER STREET LA MESA CA 91942 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 640,458.86 144,646.76 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 640,458.86 144,646.76 5. Mobilization 6. Total Work Completed 640,458.86 7. Deductions -32,200.00 -5,460.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 608,258.86 139,186.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,186.76