Dept. of Trans. PROGRESS Serial No. Contract No. 10-082-15-09 11-261504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 50% 11-IMP-8-R31.3/ .0 Federal Project: ACHS-X025(28) STPG-X025(28) Progress payment No. 07 Payment period ending: 03-20-10 R S M 2 CONTRACTORS INC 8191 CENTER STREET LA MESA CA 91942 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,148,290.34 239,133.26 2.a. Extra Work b. Adjustment Comp. -2,017.00 -2,017.00 3. Materials on Hand 4. Earned Subject to Retention 1,146,273.34 237,116.26 5. Mobilization 6. Total Work Completed 1,146,273.34 7. Deductions -32,880.00 -1,840.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,113,393.34 235,276.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 235,276.26