Dept. of Trans. PROGRESS Serial No. Contract No. 15-205-07-08 11-261604 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 11% Location: Federal Project: 11-SD-5-4.0/R22.3 NHPI-005-1(629) Progress payment No. 003 Payment period ending: 07-20-15 LB CIVIL CONSTRUCTION 11585 SORRENTO VALLEY RD 104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 489,727.40 193,194.10 2. a. Extra Work 300.00 300.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 490,027.40 193,494.10 5. Mobilization 360,000.00 120,000.00 6. Total Work Completed 850,027.40 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 845,027.40 313,494.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 313,494.10