Dept. of Trans. PROGRESS Serial No. Contract No. 11-355-13-53 11-261704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 41% 11-SD-8-3.0/12.6 Federal Project: ACIM-008-1(305) Progress payment No. 05 Payment period ending: 12-20-11 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 267,438.00 105,622.90 2.a. Extra Work 210.79 210.79 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 267,648.79 105,833.69 5. Mobilization 77,900.00 16,400.00 6. Total Work Completed 345,548.79 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 344,548.79 122,233.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,233.69